Resource Lag Duration

D
Dieter Wambach 👤 Member for 19 years 5 months

"Lag"



Out of P6 Hint Help:

"The time lag of the relationship. This is the time lag between the predecessor activity’s start or finish date and the successor activity’s start or finish date, depending on the relationship type. The time lag is based on the successor activity’s calendar. This value is specified by the project manager and is used by the project scheduler when scheduling activities."