Resource Lag Duration
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
"Lag"
Out of P6 Hint Help:
"The time lag of the relationship. This is the time lag between the predecessor activitys start or finish date and the successor activitys start or finish date, depending on the relationship type. The time lag is based on the successor activitys calendar. This value is specified by the project manager and is used by the project scheduler when scheduling activities."