Dear All,
Generally the tender schedules will be the LVL1 - CCMS (Contractors Master Schedule) which is also fit in to the CONTRACT. Majority of times the LVL4 Schedule will be requested after 14(21) workdays after signatures.
My top ten will be (For LVL1 CCMS)
1-Check for a narrative if there is an obligation in tender documents, if there is an ob. and there is not any; do not look in to the schedule
2-Check if all disciplines mentioned in LVL1
3-Check the end dates of each discipline if they are same as the tender documents.
4-Check if there are any un-fit situations with CONDITIONS of CONTRACT
5-Check the planned start of the project
6-Check if there are any total cost or manhour assumptions, check it with tender docs.
I can find only 6
Regards,
Safak
Dear R,
Elaborating on your question regarding answer #2: It depends on your project. Once the project starts then you need to submit you Program of Works and get it approved by the Consultant. If events occured and you do not have your program of works approved, then you need to revert to your Tender Schedule.
Again, it depends on the Contract you have. Did the client prepare the schedule as a part of the master plan or did the Contractor submit his schedule as part of the tender documents.
Let us know the type and size of the project and we might be able to help some more.
Kind regards,
Samer
OK Mike, I fully understand.
Cheers,
Hi R
This goes to the nub of my endeavour to promote Bottom Up Planning with a ban on Planning Abominations.
If you have an electronic copy of the programme it is easy to check if the critical path responds properly to change by putting in a dummey event and linking it to a task off the critical path.
Increase the duration of the event a bit at a time and watch when it turns critical. This should be at the same point as the total float of the impacted task.
If it turns critical sooner or later than the available float the critical path has been rigged and will not respond dynamically to change.
If you link the dummy event to a task that is showing critical then any increase in the event should show an identical increase in the completion date - allowing for holidays in the calendar - if not it has been rigged.
I have never yet created a true bottom up programme where more than on critical path has been generated - the available combinations are too vast for it to happen naturally.
There are subltle ways of taking tasks off the critical path and shifting it elswhere.
In PowerProject for instance you can take 2 hours off the duration of a critical task - it will still show the same dates and duration in days - but the critical path will shift to another route.
Best regards
Mike Testro
Mike,
Could you please elaborate more your contributions on the following:
"A more subtle check is to see if the critical path is responsive to change".
"If there is more than 1 critical path the programme has been rigged".
Best regards,
R. Catalan
Samer,
In my question # 2, if you allow them to refer to Tender Schedule for EOT claim and theres dicrepancies against the approved Contract Baseline Schedule, what will be the order of precedence?
Best regards,
R. Catalan
Hi Nestor
With all due respect to every conributor there is still room for some gentle leg pulling now and then.
Best regards
Mike Testro
Lets give due respect to every post. Its all mean to share ideas no more no less.
Cheers,
Hi R,
It depends on the size and type of project. If it is a major project then you will be dealing with high level Milestone Schedule. On the other hand, if it is a regular project with detailed information about the activities and the duration that each activity will take, then use Mikes recommendations and proceed with asking for all the details of the regular schedule.
Hi Mike,
Glad to hear from you. I always sign with the time shown on the letter as well. It would be a nice touch to add the seconds from now on.
With kind regards from Jordan,
Samer
Hi R
A more subtle check is to see if the critical path is responsive to change.
If there is more than 1 critical path the programme has been rigged.
You need an electronic copy for this check.
Things to be wary of are:
1. Start restraints
2. Lead Lags
3. SS - FF links
Also check the calendars and work patterns to see if they replicate the anticipated work conditions.
Best regards
Mike Testro
Hi Samer
I have noticed an interesting trend in your threads in that you are timing your input.
I think this should be encouraged to all PP members.
This one took me 135 seconds.
Best regards
Mike Testro
Dear R.,
Answer #1 quick review in 5 minutes of less:
1. Correct WBS.
2. Constructability.
3. Complete BOQ items included.
4. Include sufficient review period.
5. Check for long lead items.
6. Check for works completed by others.
7. Identify Milestones and their schedule.
8. Check for Payment schedule
9. Ensure handing over dates of the site is shown.
10. Make sure that the review period of all submittals is shown on schedule.
Answer #2: Of course. It is part of the Contract documents.
Best Regards,
Samer