long activity description

F
faik ulku 👤 Member for 17 years 2 months
S
Safak Vural 👤 Member for 18 years

Dear Faik,



You can add 2 or 3 custom data items as RUS1 and RUS2. Every item will give you 20 characters to add. If you want to show in reports you can show in layout view or in other reports. It will be easy for you just to import the descriptions.



EX:

RUSS1-FLOOR RUSS2-BLOCK RUSS3-WORKTYPE (depends on your WBS)



Safak

F
faik ulku 👤 Member for 17 years 2 months

Dear Safak



The problem is we have to present our schedules in both languages in Russian and English. I use log for russian part but log is also not enough for russian translation. that is the problem.

S
Safak Vural 👤 Member for 18 years

Dear Faik,



If you can divide the description in parts in a logical way, then you can add a activity code for the un-fit parts of the description and then you can show on the bar chart view as the columns next to activity description. Or you can add Logs to the activities.



Regards,



Safak

A
Alex Wong 👤 Member for 23 years 3 months

Hi



In P3 .... quick answer is No you cannot

In P6 .... put your description in the notebook



HTH



ALex

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts