In P3, you will get details of the project such as the following:
Number of activities, Number of activities in longest path, Started activities, Completed activities, Number of relationships and Percent complete.
Ahmed, that what i want to say, but in mimounes english ;)
thanks very much
Hi Mimoune
Performance % complete related to cost means price per unit
if your resource assign only unit...not the cost
then Performance % Complete will not help.
Shahzad
thanks Alex;
of course the resource must have unit/price assigned, otherwise performance % complete will show always 0
and to use manhour as a weight factor, we just put price as 1
mimoune
note to myself: read the manual before asking questions
Mimoune
Call up a column called performance % complete, this should mirror physical % complete and will roll up through the WBS levels
Cheers
Shimmo
hi alex, yes it is ;)
thanks in advance
Hi
Depends on whether your schedule is resource loaded
Regards
Alex
Is there any possible way to show project % complete in terms of time / effort like in P3?
Regards,
Shan
Hi Shanmugam,
In terms of time, you can use "duration % complete".
Regards.
Hi Mimoune,
I agree with James, to roll up the percentage based on physical you need to have your performnance % complete equal to your physical % complete. Then, try to change your "% complete type" from duration to physical and observe what will be the outcome.
This will only work if your programme is cost loaded.
Just try this exercise and let us know.
Hope this helps.
Regards,
Arnold