(Physical % linked to actual cost) not linked to RD

D
Dieter Wambach 👤 Member for 19 years 5 months

James

Sorry for late reply.



To translate the Autocost Rules of P3 into P6 parameters, you’ll better read pages 76 to 89 within the pdf "From P3 to P6" on your documentation cd. There are some helpful screenshots as well.



Automatted run of Global Changes: This is one of current requests from German EPC contractors to Primavera.



Regards



Dieter

J
James Braghini 👤 Member for 18 years 1 month

Mimoune:



Thanks for your help. Does anyone know how to make a global change permanant so we do not have to "apply changes" everytime?



James B.

M
mimoune djouallah 👤 Member for 19 years 8 months

James



to be honest James, i am very new to P6,( in work,we use only P3, and an in house software to evaluate physical progress).



but as far as i know, there is no dynamic links yet in primavera products.



good luck with your update;



mimoune

J
James Braghini 👤 Member for 18 years 1 month

Mimoune:



It works however, we will need to do an "apply change" to both of the new global changes to make this work. Do you concur and have a way to get around the "apply change"?



Thanks,

James B.

J
James Braghini 👤 Member for 18 years 1 month

Dieter:



Sorry about just now getting back to you. The company I work for is used to in P3 having the autocost rule unlinked between remaining duration and percent complete, with the percent complete time the budgeted cost determining the actual costs. There are so many combinations in P6 we cannot find one that does what I described above. Do you know of any combinations?



Thanks in advance,

James B.

D
Dieter Wambach 👤 Member for 19 years 5 months

James



in my opinion this combination is not possible. But what’s the business’ background?

Do you have costs which are not related to resources?



Regards

Dieter

A
Arnold Puy 👤 Member for 19 years 1 month

Hi James,



Go to Enterprise --> Project, select your current project. From Project detail, select Calculation Tabs, Resource Assignments, remove the check next to "Recalculate Actual Units and Cost when duration % complete changes".



HTH.



Arnold

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts