adding contractor schedule to original one

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Nasreen,



Yes, it is possible. But first, make sure that you have a backup of both projects.



Open the Two projects, the original project and the contractor schedule. Go to WBS workspace and copy or cut the WBS and paste to the original project.



Be sure to mark all the checkbox of the "Copy WBS Options" & Copy Activity Options" and relate or link these activities to your original project.



With regard to S-Curve, I think you need to double check the resources assigned to your activities. You can modify or change the quantity using excel sheet.



HTH.



Regards,



Arnold