Arnold Puy 👤 Member for 19 years 1 month

Hi Kevin,



First of all, WELCOME to PP.



Default Columns are the following:



1. Activity ID

2. Activity Name

3. Activity Status

4. Planned Value Cost

5. Earned Value Cost

6. Actual Cost

7. Budget At Completion

8. Estimate To Complete

9. Estimate At Completion Cost

10. Variance At Completion



Default Group & Sort:



1. Total

2. WBS (with Indent)



Regards,



Arnold