Report to show actual vs target W/O resources

A
A D 👤 Member for 19 years

define a resource and then put BQ=OD using global change



and then plot the graph

M
mimoune djouallah 👤 Member for 19 years 7 months

hi



just assign a resource to all activities " let’s call it TIME for simplification" with 1 as units per day, then you can generate your S curve



HTH