hours in p3.1

J
Juan Nichterlein 👤 Member for 19 years 2 months

Dear Friends :



The answer is a bit more complicated. Not only OD will have to be turned into hours (8 is the standard for Engineering and also for procurement, 10 is the standard for construction). You will also have to take care on relation lags, remaining durtions, constraints (it is not the same to have a constraint finish at the beggining of the day that at the end of the day), calendars and if shifts apply, you will have ti incorporate them.



My advise, if you are working on a standard EPC or EPCM long/medium term proyect, keep in days. If you are working on shutdown proyects, or complex Tie-Ins built a separate project with a Finish no later than constraint for the project, and adjust it to the timeframe provided by the master schedule.



Hope this helps, Regards

S
Safak Vural 👤 Member for 18 years

In P3, the only way that you can make that using planning units as hours, JK give you the solution. I can only add that you can arrange the work hours in the day in Calendar from bar next to the calendar.



Unless reporting progress daily this difference will not bring you any special information and you will have a shorter critical path. If you have a long term, >500 ativity project the end dates will be much more earlier that they will occur.



Regards,



Safak

J
Johny Kesserwany 👤 Member for 18 years 8 months

Make a copy of the project and change the planning unit to hours in the copy window. Then perform a global change to multiply all OD by 8!



By the way, why do you need a project in hours?



JK

K
kafo souq 👤 Member for 17 years 3 months

There is a quick fix to this



If you have SureTrak V2 or 3



Open you file in SureTrak go to options and change the display type of planning unit then pick Hours and so on for resources



Keep in mind that the default planning unit in SureTrak is hours even if it shows days (it does that using an 8 hour standrad working hours/day)



Once you change the planning unit in suretrak save your project and open it in Primavera



Job Done



Note Gee I love that little SureTrak more than P3 or P4, P5 or P6


J
Johny Kesserwany 👤 Member for 18 years 8 months

Hi,



You can’t define hours unless your planning unit for the project is in "hours", then you can find it in: Data / Calendar / Standard.



Regards

JK

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts