Updating via Importing Data from Another Project
Forum Sponsor
Top Posters
Adrian Fletcher
12 posts
GeoVe
0 posts
James Williams
74 posts
Abkar Bannayan
25 posts
christiandt
0 posts
J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Hi R Jones,
First of all, welcome to Planning Planet.
Well, it is not very clear for me however, let me answer your question. But first make a backup to your project.
In order to update your Baseline Resource Quantities, go to Project --> Maintain Baselines and select the Baseline you wanted to update.
Select the "Update" button remove all the checks except for "Update exisitng activities already in the baseline" & "Ignore Last Update Date". In Specify the activities to include: select the "All activities" or filter the folowing activities you want to change.
Then select the "Update Options" radio button, under the "When updating resource assignment data, include:
Mark the checkbox next to "Update existing resource and role assignments" & "Budgeted units and cost" & unselect the rest of the checkbox then ok.
Then select "Update".
You can easily perform this exercise in excel sheet.
HTH.
Regards,
Arnold