Convert P6 project w/baseline project to P3
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
If you want both the current schedule and the baseline schedule, you will need to restore your baseline then export both files separately.
Trevor
Hi Abeer,
Go to file menu --> export --> export format, select Primavera Project Planner - (P3) format.
HTH.
Arnold