Microsoft Project Member for 19 years 11 months Member for 19 years 11 months Submitted by Trevor Rabey on Wed, 2009-02-18 08:20 Permalink RE: extended deadline marker I answered this in microsoft.public.project Make a Milestone (duration = 0). Make the task a FS predecessor with some positive lag. Put the deadline on the milestone rather than the task. Member for 19 years 11 months Member for 19 years 11 months Submitted by Trevor Rabey on Wed, 2009-02-18 08:20 Permalink RE: extended deadline marker I answered this in microsoft.public.project Make a Milestone (duration = 0). Make the task a FS predecessor with some positive lag. Put the deadline on the milestone rather than the task. Log in or register to post comments
Member for 19 years 11 months Member for 19 years 11 months Submitted by Trevor Rabey on Wed, 2009-02-18 08:20 Permalink RE: extended deadline marker I answered this in microsoft.public.project Make a Milestone (duration = 0). Make the task a FS predecessor with some positive lag. Put the deadline on the milestone rather than the task.
Member for 19 years 11 months Member for 19 years 11 months Submitted by Trevor Rabey on Wed, 2009-02-18 08:20 Permalink RE: extended deadline marker I answered this in microsoft.public.project Make a Milestone (duration = 0). Make the task a FS predecessor with some positive lag. Put the deadline on the milestone rather than the task.
Member for
19 years 11 monthsRE: extended deadline marker
I answered this in microsoft.public.project
Make a Milestone (duration = 0).
Make the task a FS predecessor with some positive lag.
Put the deadline on the milestone rather than the task.
Member for
19 years 11 monthsRE: extended deadline marker
I answered this in microsoft.public.project
Make a Milestone (duration = 0).
Make the task a FS predecessor with some positive lag.
Put the deadline on the milestone rather than the task.