Hi Jaya.



You can use the maintain baselines under your project menu to create baselines. Keep in mind that if you create a baseline from a project that project will be removed from the projects list. You can the assign baselines to a project and select the bars if you right click the bars option on your gant chart.



The help file also contains alot of information on exporting to and importing from excel.



Hope this helps.