Niek,
who knows, its so easy to make a mistake...
well, I dont know; I could send you my file if you want, just give me your email.
Alexandre
Hi Alex, Tout va bien?
12.0.6211.1000 / SP1 MSO 12.0.6320.5000
Assigning resources to milestones, what do you take me for? :-)
Cheers,
Niek.
Niek,
Which release of MSP 2007 are you working with?
I am using MSP2007 Pro Build 12.0.4518.1214 and everything is working fine.
You should check that you do not have any resource assigned to your milestone, or that the option "Scheduling ignores resource calendar" is active
Alexandre