WBS duration

S
sonia rose 👤 Member for 17 years 7 months
A
A D 👤 Member for 19 years 1 month

Thats because WBS Durations are based on global calendar and not project calendar.



Ur global calendar must be set for 5 days a week. The issue is still not resolved by primavera and is on the list.