You could embed a hyperlink on each task to a document describing the specific calculations. It should be possible to have a bookmark as part of the link so you could go directly to the appropriate discussion in your document. Whenever you wanted to display the justification, youd just click on the hyperlink field for that task. Its not a database, but it *is* a location where you can put arbitrarily complex descriptions.
Or the hyperlink could reference an HTML file on your machine. That HTML file would have the coding in it to access the database and display the contents.
You could actually connect to a database with some VBA though Ive never tried that. The connection to the database would be non-trivial (but also well documented since Im sure there are tens of thousands of times where people have used VBA to access a database) but, after that, the coding would be simple. So you would select the task and have a button that you could click on to launch the VBA which would access the database.
Note that in all cases, you would have to supply both the project schedule and, in the first instance the document; in the second case youd need to supply the database, the database engine and the html page; in the third case, youd need to supply the database and the database engine.
In short: technically - quite doable. The real issue is time: is your time as PM better invested in monitoring the project or better invested in overseeing an additional project deliverable. Ive answered your question ... now you have to ponder your own answer to mine .
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Thanks for that I will have to think on it.
Many Regards
Andrew
You could embed a hyperlink on each task to a document describing the specific calculations. It should be possible to have a bookmark as part of the link so you could go directly to the appropriate discussion in your document. Whenever you wanted to display the justification, youd just click on the hyperlink field for that task. Its not a database, but it *is* a location where you can put arbitrarily complex descriptions.
Or the hyperlink could reference an HTML file on your machine. That HTML file would have the coding in it to access the database and display the contents.
You could actually connect to a database with some VBA though Ive never tried that. The connection to the database would be non-trivial (but also well documented since Im sure there are tens of thousands of times where people have used VBA to access a database) but, after that, the coding would be simple. So you would select the task and have a button that you could click on to launch the VBA which would access the database.
Note that in all cases, you would have to supply both the project schedule and, in the first instance the document; in the second case youd need to supply the database, the database engine and the html page; in the third case, youd need to supply the database and the database engine.
In short: technically - quite doable. The real issue is time: is your time as PM better invested in monitoring the project or better invested in overseeing an additional project deliverable. Ive answered your question ... now you have to ponder your own answer to mine .