Hi Roger,



Okey, here is the best way to do. Open the two projects. The project defined with activity codes and the other one project without the activity codes.



Go to Enterprise --> Activity Codes, Project radio button and select modify. Now, select all activity codes you want to copy & right click paste it to EPS/Project:



Regards,



Arnold

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Roger,



The other workaround on how to transfer or copy the Activity Codes by copying the project and in the "Copy Project Options" remove the check next to Activities.



Or you can use the SDK and Parser & Builder from Primavera Knowledgebase.



Arnold

M
Mike Testro 👤 Member for 20 years 5 months

Hi Roger



In powerproject you can copy / paste anything between projects.



Best regards



Mike Testro



ps try not to use block capitals - it seems as though you are shouting at us - Charleston got into a big argument on this subject.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts