Civ Oczalev 👤 Member for 17 years 5 months
D
Dieter Wambach 👤 Member for 19 years 5 months

Peter



Primavera internally calculates and memorizes everything in hours. But if you’ll display 0h in days it will be 0 independent from settings. A change between 0 and 1 means that there is no zero-float. Display your durations with decimals and it will be evident.



Regards

Dieter

P
Peter Nicol 👤 Member for 17 years 4 months

gotta love Primavera’s "Features".



this is an issue i’ve run into previously.



In particular where i have a job where i have engineering and construction activities. More often than not these 2 are on different calenders which is a big issue when displaying durations in days, weeks or months (usuaully days) as we all know what happens as a result of the user settings :P



in this situation i ended up displaying hours instead anyway. it’s ugly but there is easy solution here.



I’m aware of the float issue with regards to this. This greatly impacts the critical path if you are using the = or less than 0 days critical path option. P6 can actually miss the critical path as a result of calender changes. I’ve activities on the the critical path deviate between 0 days and 1 day even though they drive each other. this deviation is a result of calender changes. i do hope Primavera solve this soon.



- Peter.

S
Shahzad Ahmad 👤 Member for 18 years 4 months

Hi Dieter



Thanks for your reply.

Really i was not aware of this setting ..



i will try in next project if it will work for me.





Thanks



Shahzad

D
Dieter Wambach 👤 Member for 19 years 5 months

Shahzad

This I cannot support.

We use different calendars. There is no problem if you are aware of some details:

- Floats, durations in summary lines base upon default calendar, don’t display them.

- Float of an activity is based upon the activity’s calendar

- Lags depend on your scheduling options.

Different floats on a longest path are misleading, so don’t show them. Primavera promised an improvement, e.g. an additional column with a float based upon the project calendar.

Regards

Dieter

S
Shahzad Ahmad 👤 Member for 18 years 4 months

hi,



use of more then one calender not advisale in P6 By Paul Harris.



If you want to change All activites claender there Should no harm.

D
Dieter Wambach 👤 Member for 19 years 5 months

Civ

I don’t really understand your quetion, so a little general reply.

Modifications of calendars in general: Grant the right to change general calendar to very few persons. Give "speaking" names to calendars, e.g. 5d_10h_PhilippineHoliday. Have a discussion for the default calendar because all summary calculations are based on this one.

To change activity calendars for many activities, use "Fill Down".

Hope that helps

Dieter

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts