I've tried it as well and had the same issue: my settings were "Fixed Duration and Units" and "Physical % Complete."
I think the issue is that Physical % and Labor units do not seem to be directly related. As such, I would able to update the actual units under the Acitivity Resources Tab, and manually updating the "Actual Units" heading. If you don't see it under your resources tab, you would need to right click "Customize Resource Columns".
Are you using physical or duration as the % complete? Also do you have an actual start against the activity? If no actual start and/or physical % complete = 0 then no progress will be recorded
PS - Duration type doesn’t impact whether an activity earns or not.
when you changed the percent complete type to physical - did you enter a % in the physcial column (ie. type it in) (i am just checking).
To see whether you are earning @ an activity level... in the activity view add the column "Performance Percent Complete". If you have setup the WBS correctly (earned value settings) for calculating performance percent complete. This should equal either duration, physcial or units (depending on which percent complete type you have set the activity too).
If all of the above is working then its worth also showing the "Budget at Completion - labor units" column too.
remember :
earned value - labor units = performance % complete x BAC - labor units.
so those 2 fields i mentioned must not be 0 to work.
PS - if BAC is 0, then there is something wrong with your baseline.
Remember if you want to rollout performance % complete (you will need costs in the schedule - even if they are an average rate)
- jajang
Member for
18 years 9 months
Member for18 years9 months
Submitted by Dieter Wambach on Sun, 2009-02-01 04:07
Im personally new on here.. but i have your answer.
quick explanation of how P6 calculates EV:
Earned Value = Performance % complete x Budget at completion (usually your baseline)
Performance % complete = Activity % complete (this is the default setting unless you have changed it at a WBS level)
Activity % complete = Percent complete type (duration, units or physcical)
In this case you likely have your percent complete type = duration (correct ?)
Now duration % complete = 0% in the above case because you still have 7 days left of the work which says that you have still not earnt any work by this case (of course this is not the case so i would recommend you use Physcial % complete for this if you want to use EV correctly - this means you enter the % complete manually yourself when updating - ie. you would need to work that % out by looking at the physical work done (in real life that is)
Member for
16 years 3 monthsthis post is from 2009 not
this post is from 2009 not sure that its still revelant over a decade later
Member for
6 years 9 monthsCiv,I've tried it as well and
Civ,
I've tried it as well and had the same issue: my settings were "Fixed Duration and Units" and "Physical % Complete."
I think the issue is that Physical % and Labor units do not seem to be directly related. As such, I would able to update the actual units under the Acitivity Resources Tab, and manually updating the "Actual Units" heading. If you don't see it under your resources tab, you would need to right click "Customize Resource Columns".
I hope this helps.
Please See attached Photo
[[wysiwyg_imageupload:7861:]]
[[wysiwyg_imageupload:7858:]]
Member for
12 years 8 monthsAre you using physical or
Are you using physical or duration as the % complete? Also do you have an actual start against the activity? If no actual start and/or physical % complete = 0 then no progress will be recorded
Member for
16 years 9 monthsRE: P6 Updating (Labor Units not Earning)
PS - Duration type doesn’t impact whether an activity earns or not.
when you changed the percent complete type to physical - did you enter a % in the physcial column (ie. type it in) (i am just checking).
To see whether you are earning @ an activity level... in the activity view add the column "Performance Percent Complete". If you have setup the WBS correctly (earned value settings) for calculating performance percent complete. This should equal either duration, physcial or units (depending on which percent complete type you have set the activity too).
If all of the above is working then its worth also showing the "Budget at Completion - labor units" column too.
remember :
earned value - labor units = performance % complete x BAC - labor units.
so those 2 fields i mentioned must not be 0 to work.
PS - if BAC is 0, then there is something wrong with your baseline.
Remember if you want to rollout performance % complete (you will need costs in the schedule - even if they are an average rate)
- jajang
Member for
18 years 9 monthsRE: P6 Updating (Labor Units not Earning)
Civ
Fixed duration and units means you plan with:
- fixed duration and modify for started activities by remaining duration or expected finish date
- fixed units and modify for started activities by remaining units
Youll have to regard both.
Regards
Dieter
Member for
16 years 9 monthsRE: P6 Updating (Labor Units not Earning)
I tried "physical %" but it did not earn units.
I tried "units %" and it earned units.
Is this alright or one of my settings is incorrect?
BTW my "Duration Type" is Fixed Duration & Units.
Member for
16 years 9 monthsRE: P6 Updating (Labor Units not Earning)
Hi there civ,
Im personally new on here.. but i have your answer.
quick explanation of how P6 calculates EV:
Earned Value = Performance % complete x Budget at completion (usually your baseline)
Performance % complete = Activity % complete (this is the default setting unless you have changed it at a WBS level)
Activity % complete = Percent complete type (duration, units or physcical)
In this case you likely have your percent complete type = duration (correct ?)
Now duration % complete = 0% in the above case because you still have 7 days left of the work which says that you have still not earnt any work by this case (of course this is not the case so i would recommend you use Physcial % complete for this if you want to use EV correctly - this means you enter the % complete manually yourself when updating - ie. you would need to work that % out by looking at the physical work done (in real life that is)
- Pete