Cost Estimation Versus Cost Controlling

R
R. Catalan 👤 Member for 20 years 9 months

Izam/Samer,



If I may add to the discussion and in addition to what Samer has said;



S-curve can be develop by showing:



For Accounts section:

Cash In/Out (Payment In from PCs / Payment out to suppliers, subcons, etc.), and could be track by comparing planned vs. actual



For Cost Control:

S-curve that will show

Planned Value (PV or BCWS)

Earned Value (EV or BCWP)

Actual Value (AV or ACWP)


S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Izam,



You are correct, you always have two reports. One from site and the other is from your Financial Department controling the spenditure on the project.



Best Regards,



Samer

I
Izam Zakaria 👤 Member for 20 years

Is it fair If I’m declare that Cost actual will equivalent with progress actual? It won’t right? Is all about how we run capex and opex? So the question how we do to manage it? Is it we will come out two reports of S-Curves and monitoring report?

S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Izam,



Cost Estimation is done prior to the start of the project.

Cost Control is done once the Letter of Commencement is issued to the Contractor.



Usually you will have a budget (excel or other) stating the amount of money dedicated for every activity required to complete the work. You can start with general headlines like; Design, Engineering, Procurement, Fabrication, Excavation, Construction, Erection works, Testing and Comissioning.



Testing and commissioning cost depends on the equipment that you are testing. This can be a large Turbine or a small HVAC equipment. And it can be done by specialist with fixed contracts.



Hope this information was helpful.



Best,



Samer

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts