You need to set the percentage complete type;
a. Duration (DEFAULT)
b. Units
c. Physical
If you are going to update a resource driven activity based upon the no. of units of the resources consumed, then you better set the % complete type as units.
Alternatively, if you are going to update % complete based upon duration, then what you can do is to set project-details-calcuation tab you can set RECALCUALTE ACTUAL UNITS AND COST WHEN DURATION %......., so that when you update duration %, the same value is automatically set to update units %. But in this case units % and duration % cannot be different. However in the first method you can treat them differently. ie. when 60% of the duration is completed, only 40 % of resources units is completed, showing a loss of productivity and vice versa.