Resource driven activity

M
MATHEW JOSEPH 👤 Member for 21 years 11 months

You need to set the percentage complete type;

a. Duration (DEFAULT)

b. Units

c. Physical

If you are going to update a resource driven activity based upon the no. of units of the resources consumed, then you better set the % complete type as units.



Alternatively, if you are going to update % complete based upon duration, then what you can do is to set project-details-calcuation tab you can set RECALCUALTE ACTUAL UNITS AND COST WHEN DURATION %......., so that when you update duration %, the same value is automatically set to update units %. But in this case units % and duration % cannot be different. However in the first method you can treat them differently. ie. when 60% of the duration is completed, only 40 % of resources units is completed, showing a loss of productivity and vice versa.

Forum Sponsor

Top Posters

sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts