Budgeted Quantity (with Different Cost Category)
Forum Sponsor
Top Posters
Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Dear Ferdinand,
Thank you. It worked.
Create Data Custom: Assign BQL-Labor BQ & BQM-Matl BQ
for Manpower
if: CAT eq L
then: BQL eq BQ (or BC if Cost)
for Material
if: CAT eq M
then: BQM eq BQ (or BC if Cost)
Mr. Iimos,
Yes, I know how to use the Global Change, but my main problem is how to provide logic to it applicable to what I need. I tried using the logic for Cost Category but failed. I even filtered first the schedule based on resources containing Cost Cat. of "M" and "L" but was unsuccessful. More help plss....
first go to Data, Custom Data Items, create your items, then play with global change
Anoon,
Maybe yes, but I tried doing the global change but was unsuccessful after a series of trials. Can you please provide me more details on how to execute your suggestion.
Regards.
Jun
if I remember correctly, I think you can use custom data items and make some global changes to suit what you need.