Samer,
Thanks for the reply. However, am not sure if you referring Percent Expended wherein the percentage of actual cost which has been spent to date. And Percent Complete is the percentage of the activity which is complete. Thus, my query refers to the automatic updating of the percent complete both for the activity and cost form. Unless otherwise let Suretrack to calculate the Percent complete. But my program is applied on a manual updating coz im controlling the completion dates of each activity based from the availability of our resources and milestones.
Dear Ferdinand,
If your program is linked together correctly, then it should work, yes.
Best,
Samer