Aluminum Smelter Schedule

S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Mohammed,



You are talking about a huge project.

I would suggest that you divide the project into Zone or buildings. Then you can start working on the schedule for each.



Each building will need the following:



1) Site survey

2) Excavation

3) Substructure

4) Pre Engineered Building

5) Electromechanical

6) Commissioning



Depending on the parts of the project that you will be working on, I might be able to assist with the list of activities and sequence of work.



Best Regards,



Samer