Q&A by oneself. I feel amused and I dont get the subject.
my understnading over your questionis you want to update your schd. based on your judgement.
while you updating your schedule based on Physical % complte manually
just set (% complete type) accordingly,
Steps
Activity Type Duration tpe % complete Type
Task Dependent fixed unit... (set here )
easy way to set Physical % complete,
Good Luck