Resource Labour Planning Overview
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
This is may be a solution for your problem if I have understood it correctly:
1- Open alle the projects where you have assigned resources
2- Go to Group and Sort and then choose resource IDs to make the grouping.
Ian,
Excel is not the proper tool - it is too hard to synchronize schedule changes with Excel.
I hope that you will receive satisfactory answer in PM5/PM6 discussion. If no, you can try Spider Project that is much more powerful in resource planning.
Best Regards,
Vladimir
Vladimir,
Thanks for the response. I figured this was the right topic forum, but if not, I will add it under the one you suggested.
I have tried doing it in P5/6 but the result was not ideal so I did it in Xcel. Was just hoping to get more out of our P5/6.
Regards
Ian
Ian,
why do you ask this question in this thread instead of PM5/PM6 discussion?
Your question has very simple answer if to use Spider Project (just open Resource Gantt), but you need PM5 advice, isnt it?
Best Regards,
Vladimir