This is may be a solution for your problem if I have understood it correctly:

1- Open alle the projects where you have assigned resources

2- Go to Group and Sort and then choose resource IDs to make the grouping.


V
Vladimir Liberzon 👤 Member for 25 years 4 months

Ian,

Excel is not the proper tool - it is too hard to synchronize schedule changes with Excel.

I hope that you will receive satisfactory answer in PM5/PM6 discussion. If no, you can try Spider Project that is much more powerful in resource planning.

Best Regards,

Vladimir

I
Ian Perrins 👤 Member for 17 years 8 months

Vladimir,



Thanks for the response. I figured this was the right topic forum, but if not, I will add it under the one you suggested.



I have tried doing it in P5/6 but the result was not ideal so I did it in Xcel. Was just hoping to get more out of our P5/6.



Regards

Ian

V
Vladimir Liberzon 👤 Member for 25 years 4 months

Ian,

why do you ask this question in this thread instead of PM5/PM6 discussion?

Your question has very simple answer if to use Spider Project (just open Resource Gantt), but you need PM5 advice, isn’t it?

Best Regards,

Vladimir

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts