Shazia khan 👤 Member for 18 years 1 month
D
Dieter Wambach 👤 Member for 19 years 5 months

Shazia



If you have cd: No. 3 (Dok) --> From P3 to P6

DVD: Client Applications --> English --> Dokumentation --> from ...



The RefManual has a good index and is very much in detail. Maybe you’ll ask for a training.



Good luck!

Dieter

S
Shahzad Ahmad 👤 Member for 18 years 4 months

Hi-Dieter



Thanks for your guidline



P3 schedule is without resources loaded.



Client urge prepared schedule in P6 for the entire project included all resource,



Client wants every thing in P6 Reporting , Histogram all Curves etc.



I got only P6 Manual i do not have other CDs & Dvds,,may be they will be head office,



Could you Please send relvent topic as you advise me to look up them in Cds.



Regards

Shazia




D
Dieter Wambach 👤 Member for 19 years 5 months

Shazia

The import will create the resources assigned in P3 automatically. As P6 has more parameters than P3, check and add.

On your P6 cds or dvd you’ll find under dokumentation --> "from P3 to P6" an excellent documentation. Read the help function, it will be a great support for you.

Good luck

Dieter

S
Shahzad Ahmad 👤 Member for 18 years 4 months



as sample as just import your P3 Schedule in P6



check all relation and actives have been imported.



thenyou can create a resource directory.listed out your resource in that.set there units and cost as required for your projects.



then assign resourcess to the activities acoordint to there nature.



may be some one else explain better then me

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts