You can also save upto ten baseline positions if you cant save copies of your schedule for some reason e.g. if you have live links to other projects. As an added bonus your gantt chart will have lots of coloured lines for each of the baseline positions which will baffle with science anyone who does not know much about schedules e.g. the management team. It does come in handy for getting snapshots and identifying trends against your original baseline over time, and you would be able to show in a report just the columns from previous months where you have baselined if you wanted.
Project, Project Information, set the Status Date.
After you set the Status Date to, say, some date a month ago, select all Tasks and hit the "Update As Scheduled" button on the Tracking Toolbar.
See the Tracking Table for % Complete for every Task.
Job done.
However,if you are going to look for the planned % Complete (as well as the planned everything else) for a month ago, you must use the plan that was the current plan on that date. You cant use this weeks plan for the status of a month ago.
Thats one (more) reason why you should save a copy of the plan every day, rather than just overwriting it every day.
However I am looking for a summary report page telling me % complete as of last month etc.
Oddly enough I think I have found the answer, by going back in time! Yes by altering the time clock on the PC back a month, then printing out a summary report!
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Andrew,
You can also save upto ten baseline positions if you cant save copies of your schedule for some reason e.g. if you have live links to other projects. As an added bonus your gantt chart will have lots of coloured lines for each of the baseline positions which will baffle with science anyone who does not know much about schedules e.g. the management team. It does come in handy for getting snapshots and identifying trends against your original baseline over time, and you would be able to show in a report just the columns from previous months where you have baselined if you wanted.
Regards,
Will.
Hi Andrew,
Do you archive your project files??
If I want to run a report retrospectively, I’ll just use a file from that reporting period.
Regards,
Darren
Andrew,
You dont need to re-set the computer.
Project, Project Information, set the Status Date.
After you set the Status Date to, say, some date a month ago, select all Tasks and hit the "Update As Scheduled" button on the Tracking Toolbar.
See the Tracking Table for % Complete for every Task.
Job done.
However,if you are going to look for the planned % Complete (as well as the planned everything else) for a month ago, you must use the plan that was the current plan on that date. You cant use this weeks plan for the status of a month ago.
Thats one (more) reason why you should save a copy of the plan every day, rather than just overwriting it every day.
Hi Andrew,
You cab also take the advantage of using formula on fields.
Regards,
Ronald
well done dr. who
Thanks Colin
However I am looking for a summary report page telling me % complete as of last month etc.
Oddly enough I think I have found the answer, by going back in time! Yes by altering the time clock on the PC back a month, then printing out a summary report!
Needs must
Thanks
Andrew
Andrew
I would filter the tasks that are in that time frame.
Project/filtered for /date range
Select dates
Then, under the print options - select the date range you require.
File / print (timescale)
select dates
Hope this helps
Colin