Precentage for overall project in p6

A
Amro Ahmed 👤 Member for 17 years 6 months
S
Sampath Lakshmi Narayanan 👤 Member for 18 years 4 months

Still U can do one thing. U start entering Physical progress percentage in Duration % zone and re check ur remaining duration and expected completion date. This can your problem as physical percentage in Primavera does not have much impact on schedule. Even better way is assign weightages to your WBS and activities in excel, distribute in using start and finish dates and calculate the percentage progress (By Making S Curve)

J
James Shimmon 👤 Member for 19 years 5 months

In order to get a BCWS for the project to date you need to allocate costs and resources to the activities

A
Amro Ahmed 👤 Member for 17 years 6 months

i know that but the precentage based on duration usulaly not very accurate i want to get precentage based on real progress from overall activities

S
Sampath Lakshmi Narayanan 👤 Member for 18 years 4 months

No problem..You Update the schedule with the latest data date and run the schedule. You will be getting the latest Duration percentage progress ....

Forum Sponsor

Top Posters

J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts