What is "Activity Resource Assignment" ?
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Thanks a lot everybody.
Youre welcome Rav.
Thanks Dear,
Thanks a ton
Hi Rav,
Resources can be assigned to the same activity more than once. This option can be found in the Project Detail --> Resources Tab under Resource Assignments.
Regards.
It means resource assigned for an activity. There is no such specific option/tab in P6 for activity resource assignment.
There r two things to watch for resource assignment:
1. Go to Edit --> User Preferences --> Calculations.
The calculation tab has two options:
a) With the first option, each resource hours are calculated independently.
b) In second option, total no. of hours assigned to an activity will stay constant and sunsequesnt resources are added or removed from an activity. However, this option doesnt work, if activity type is FIXED DURATION and Units/Time.
2. Resources can be assigned to the same activity more than once. I forgot now where this option is, but may be somebody from teh forum can help on this.
Wish u a very happy new year
Cheers,
Rav