Recurrent Tasks

A
Ali Farhat 👤 Member for 17 years 7 months
D
Dieter Wambach 👤 Member for 19 years 5 months

You can ask Primavera, of course. Via your Primavera vendor or directly. It is a customer-driven product.

A
Ali Farhat 👤 Member for 17 years 7 months

Isnt there a way to ask primavera company or Oracle to add this feature? It can be added to activity types.

D
Dieter Wambach 👤 Member for 19 years 5 months

Ali

Recurrent tasks do not exist in Primavera.

For my experience those are tasks such as meetings, reports etc. which are important but no need to trace if they were on time.

In general I use the type level of effort and assign the resources with an appropriate rate, e.g. 2 hours a week.

If you must trace if they were done one time you’ll need an activity per period.

Sorry, no ideal solution.

Regards and a happy new year!

Dieter

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts