long lead delievery items schedule

S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Bilal,



You will need to review your Electromechanical Contract requirements in particular.



Usually long lead items include systems like:

Lifts

Kitchen & Laundry Equipment

Lighting Fixtures

Low Current systems

HVAC equipment

Fire Fighting Pumps

Generators and Package Units.



If you are importing Finishes works, then you will need to check on the approval, manufacturing, delivery and custom clearing procedures.



It is always advisable to have all the information in one place in order not to forget bits and pieces. So include you long lead items in your Procurement Section in your Main Schedule and link it to Material submittal and to the start of Construction.



Good luck,



Samer

A
Ashutosh Nema, PMP 👤 Member for 18 years

Dear Bilal,

Most important aspect in Long lead items are the manufacruring time,shipment and custom clearance(if applicable).

You can make this schedule in Excel as a Procurement schedule and put duration from tender preparation to delivery on site+time for inspection in Primavera shedule.

Items related to MEP are mostly the long lead items.



Regards

Ashutosh

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts