I’m not sure of the terminology for the French MS Project version, but you can use the Gantt Chart Wizard (Format > Gantt Chart Wizard).
As you scroll through the Wizard, you’ll see a radio button entitled ‘Custom task information’. You should be able to align the text as you wish using this option.
I think you can also format the bar styles as well (Format > Bar Styles > Text tab).
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Nicolas,
Sorry I misunderstood your post, I don’t think you can change the alignment for text inside the bar. There is only the default (align left).
Regards,
Darren
Tks Darren,
But in my French Version of MSP (2002)
you can chose what text you show right or left
of the bar or inside the bar,
but what I would like to do is not only chose
the text (remarks as a matter of fact)
but also center it in the middle of the bar
I see no option either in
Custom task information’
(Infos sur la tâche personnalisées)
or in Format > Bar Styles > Text tab
Format/style des barres, onglet Texte
Hi Nicolas
I’m not sure of the terminology for the French MS Project version, but you can use the Gantt Chart Wizard (Format > Gantt Chart Wizard).
As you scroll through the Wizard, you’ll see a radio button entitled ‘Custom task information’. You should be able to align the text as you wish using this option.
I think you can also format the bar styles as well (Format > Bar Styles > Text tab).
Regards,
Darren