P6.1 Exporting baselines

R
Roger Booth 👤 Member for 19 years 7 months
R
Roger Booth 👤 Member for 19 years 7 months

I have just had an e mail from my client suggesting just that.

Thanks for your reply



Roger

J
Joao Ribeiro 👤 Member for 23 years 2 months

Of course you can allways recover the baseline as a project and send it to your client as a XER.



HTH

R
Roger Booth 👤 Member for 19 years 7 months

Seek and ye shall find



Found this in the PM handbook



"Timesheets and baselines are not exported when you export project data. With the appropriate access, you can export secure codes and secure code assignments to XML format; however, you cannot export them to XER format. For more information about secure codes, refer to Primavera’s Administrator’s Guide."



Thanks anyway



Roger

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts