Well, MS Project does work with productivities to a certain degree, but you have to do a bit of customized fields before it works in a simple way, so admitted it is maybe not as clever carried out as in SpiderProject (not that I know it) and in other planning software that have this features.
Anyway, in MS Project you can introduce e.g. a Number1 column containing your quantities, Number2 contains your resource productivities and Duration1 the product of Number1 and Number2. Duration1 maybe need some touching up with INT()functions and a factor depending of what unit (hours, days, etc.) you calculate in. Then copy by paste special / paste links from Duration1 into Duration.
Now all durations will change when you change quantities and resource productivities and actvities will move acoording to their links.
You could also introduce a Number3 column containing your buffer/contingency/safety time for each activity, e.g. 5% extra for time to this activity and 10% to this activity, before calculating Duration1 and pasting links into Duration.
In Spider Project you can define the quantities of work to be done (work volumes) and assigned resource productivities. The rest will be done by the software.
You can also create the database of resource productivities on typical assignments and use this database in your projects. In this case it will not be necessary to enter resource productivities for the repeated types of work.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Well, MS Project does work with productivities to a certain degree, but you have to do a bit of customized fields before it works in a simple way, so admitted it is maybe not as clever carried out as in SpiderProject (not that I know it) and in other planning software that have this features.
Anyway, in MS Project you can introduce e.g. a Number1 column containing your quantities, Number2 contains your resource productivities and Duration1 the product of Number1 and Number2. Duration1 maybe need some touching up with INT()functions and a factor depending of what unit (hours, days, etc.) you calculate in. Then copy by paste special / paste links from Duration1 into Duration.
Now all durations will change when you change quantities and resource productivities and actvities will move acoording to their links.
You could also introduce a Number3 column containing your buffer/contingency/safety time for each activity, e.g. 5% extra for time to this activity and 10% to this activity, before calculating Duration1 and pasting links into Duration.
Regards,
Bo
MS Project does not work with productivities.
I recommend to look at Spider Project http://www.spiderproject.ru/demo_e.php
In Spider Project you can define the quantities of work to be done (work volumes) and assigned resource productivities. The rest will be done by the software.
You can also create the database of resource productivities on typical assignments and use this database in your projects. In this case it will not be necessary to enter resource productivities for the repeated types of work.