Small Building Projects

A
Ahmed Khan 👤 Member for 17 years 6 months
T
Tommy Nug 👤 Member for 18 years 6 months

Hi Maask,



Could you provide me some overviews of the project? I shall help you to work out the schedule.



Cheer,



Tom

A
Ahmed Khan 👤 Member for 17 years 6 months

Thank U Mr. Anoon Iimos,



I am expected for the detailed sequence of activities..



Regards



Maask

A
Anoon Iimos 👤 Member for 19 years 8 months

1. Preliminaries (including mobilization)

2. Layout (Survey)

3. Earthworks

4. Concrete Works

4.1 Foundation

4.2 Columns / Beams

4.3 Slabs

5. Architectural Works

6. MEP Works

7. Fit-out

8. Close-out



for task sequencing, you can define it in your schedule

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts