Locking in open-started activities before scheduling

D
David Kelly 👤 Member for 21 years 7 months

When you import a project that had external relationships the "External" date fields are populated. So the "External early finish" is when the predecessor from the missing project finished.



Move those dates to a Start-on-or-after constraint and the job is done.

M
Minnaar Fourie 👤 Member for 19 years

I have tried doing the "Ignore relationships to and from other projects" but it does not work. I guess it only works if there is a link to an exterternal project, which in this case, there aren’t any links because only one project was exported in xer format. I had to do it manually by identifying open started activities and then putting a constraint on each one, thereby locking in the dates.

A
Arnold Puy 👤 Member for 19 years 1 month

Hi,



Before scheduling (F9), try to go to option and mark the checkbox next to "Ignore relationships to and from other projects".



Just try this.



Arnold

A
Ali Farhat 👤 Member for 17 years 7 months

the setting you are looking for is the "Constraint"

ofcourse you have to ,manually put a constraint, but that is not complicated, you can do it in Global change or manually after filtering out all "external linked activities"

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts