change working days

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Faisal,

Tools, Change Working Time, then click the Workweek tab, and the Details button,

Select Saturday and Sunday in the list and click the 3rd option: Nondefault Working Time radio button

saïd aïdek

Alexandre

D
Darren Kosa 👤 Member for 18 years 3 months

Hi Faisal,



I can’t quite remember if it is the same for 2k7, but in 2k3 it’s Tools > Change Working Time.



In the Change Working Time dialog box, select which calendar you want to change, click the header in the Saturday and Sunday columns (this should highlight each Saturday and Sunday in the calendar) and click the Nondefault Working Time radio button.



Regards,



Darren

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts