Arnold Puy 👤 Member for 19 years 1 month

Hi Hatem,



I addition to what Ronald said, check your user prefences -> Dates -> Time, check the box next to 12 hour. Check your project must finish date against with your Activity finish date. try to change the 12:00AM to 5:00PM



Try to compare these two things, thy must be equal in date and in time.





Regards,



Arnold

R
Ronald Winter 👤 Member for 23 years 5 months

P5 works in hours & minutes but you have elected to view the results in days. This means that it has to round -0.5 days of float up to read “-1.” Change your user preferences to view hours and minutes and to see your durations with decimal fractions and you will probably see the cause of your odd reading. Good luck!

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts