Night Shifts & Day Shifts

S
Samer Zawaydeh 👤 Member for 17 years 11 months

Dear Chris,



You need to review your resource calender. This you need to read up on it. A calender for the day shift and another Calender for the night shift. Then you associate each resource with their calender. And each activity with its required resources to complete it.



Good luck,



Samer