Exporting/Importing Projects

C
Catherine Barthelemy 👤 Member for 18 years

Arnold,





Just tried and it’s just what I needed!! Simple solution really, once you’ve thought of it that is...!

Thank you very much for your time!



Catherine

A
Arnold Puy 👤 Member for 19 years 2 months

Hi Catherine,



If you want to export a project into .xer file without any resources, all you have to do is to make a copy of the project you wanted to export. while pasting it into new project, In "Copy Activity Option" dialog box remove the check next to "Resource & Role Assignments" then OK.



Export the newly copied project without any resources in it.



You can import project without the resources by creating new Update Project Options then modify. Under "Data Type: Global" for Resource Codes, Values, Roles & Resources select "Do Not Import". Make sure that the one you created make use as a default.



HTH.



Arnold

Forum Sponsor

Top Posters

J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts