dear all thanks for clarifing my que4ies but one question still remains unanswered if i have finished allocaying rresources nad then it shows(MSP 2007) that some of the resources are overallocated how do i now go about allocating the resources properly.
And the work will be postponed because Carpenter 1 assigned to it is at the scheduled moment busy on the other work but Carpenter 2 is free but not assigned.
It is not a good solution unless the package supports skill scheduling. MS Project does not support it, so the solution is not practical.
This, and the assignment stacking, determines when the Resource becomes over-allocated.
Maybe you have one carpenter assigned to a Task at 100% and another at only 20%, so thats 120% on the Task.
So you have > 50 people per trade, maybe 8 trades, so maybe 450 people. Make a list of their names and assign them to Tasks. Mostly, they will be assigned at 100%. If you dont know their names, then call them:
Carpenter 1
Carpenter 2
.
.
Carpenter 2
etc.
It makes for a long list but is much better than Carpenters at Max Units = 5000%, which is much harder for you to control and leaves all of the deployment to be managed ad-hoc at site level.
Darren has given a very good answer. He did miss one vital point off.
If your carpenter has been assigned in the resource sheet as 400%. This means you have 4 of them (I hope this answers Thomass question).
You have overloaded resources (red) when the plan dictates you need more, eg 5 tasks happening concurrently all requiring 1 carpenter.
Your options are to find an extra resource or move one of these tasks. Now all good planning tools will have a resource leveling option to do this for you. Tools and Level Resources.. in MSP. Using this option it will move the overloads depending on constraints - if you have no float then it may do nothing.
To be honest this can get quite complex - I suggest you save a copy of your plan in case you dont like the results.
I am not sure if Ive ever used this option in MSP but I have used it in P5.
if the single trade (eg carpenter) was given 400%, what does it mean? does it mean 4 units of carpenter? If my project has a lot of different trades, eg welder, grinder, fitter and so on. Plus, we are looking at the number of >50 units for each trades. What should I do? Thanks and appreciate help.
It looks like you’re using trades (bricklayer / carpenter) instead of named individuals (John Smith / Fred Smith). MS Project doesn’t know this and assumes that each entry in your resource sheet is a single individual.
You know that you’ve got more than one carpenter working on the roof, but MS Project doesn’t. It thinks that the resource you have scheduled to do the roofing has more work assigned than they can physically complete in the allotted timescale. That’s probably why it’s showing as an overallocation.
Try looking at the Resource Graph (View > Resource Graph) and then deciding for yourself whether or not they’re actually overallocated.
As an example if their peak units are 400% but there are five carpenters on the job, then they’re not overallocated. If their peak units are 400% and there are only two carpenters then they are.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
dear all thanks for clarifing my que4ies but one question still remains unanswered if i have finished allocaying rresources nad then it shows(MSP 2007) that some of the resources are overallocated how do i now go about allocating the resources properly.
But how to assign 4 units for half time?
In responce to Thomass point MSP can use units. To change from percentage go to
Tools>Options>Schedule
Show assignment units as a or
Select Decimal from the drop down list. Then you can assign as 1 for full time or 0.5 for half the time etc
And the work will be postponed because Carpenter 1 assigned to it is at the scheduled moment busy on the other work but Carpenter 2 is free but not assigned.
It is not a good solution unless the package supports skill scheduling. MS Project does not support it, so the solution is not practical.
In the Resource Sheet, see the Max Units field.
This, and the assignment stacking, determines when the Resource becomes over-allocated.
Maybe you have one carpenter assigned to a Task at 100% and another at only 20%, so thats 120% on the Task.
So you have > 50 people per trade, maybe 8 trades, so maybe 450 people. Make a list of their names and assign them to Tasks. Mostly, they will be assigned at 100%. If you dont know their names, then call them:
Carpenter 1
Carpenter 2
.
.
Carpenter 2
etc.
It makes for a long list but is much better than Carpenters at Max Units = 5000%, which is much harder for you to control and leaves all of the deployment to be managed ad-hoc at site level.
And how you will define that there is a need for 4 resource units with 50% workload on some activity?
thanks mark. one question, why does MSP go by percentage for resource and not by unit? what does that mean? can we have 120% for a trade?
Darren has given a very good answer. He did miss one vital point off.
If your carpenter has been assigned in the resource sheet as 400%. This means you have 4 of them (I hope this answers Thomass question).
You have overloaded resources (red) when the plan dictates you need more, eg 5 tasks happening concurrently all requiring 1 carpenter.
Your options are to find an extra resource or move one of these tasks. Now all good planning tools will have a resource leveling option to do this for you. Tools and Level Resources.. in MSP. Using this option it will move the overloads depending on constraints - if you have no float then it may do nothing.
To be honest this can get quite complex - I suggest you save a copy of your plan in case you dont like the results.
I am not sure if Ive ever used this option in MSP but I have used it in P5.
if the single trade (eg carpenter) was given 400%, what does it mean? does it mean 4 units of carpenter? If my project has a lot of different trades, eg welder, grinder, fitter and so on. Plus, we are looking at the number of >50 units for each trades. What should I do? Thanks and appreciate help.
thanks darren
but there are some other complications arising as well let me connfirm it then ill get back to you for more reccomendations and advice
Hi Faisal,
It looks like you’re using trades (bricklayer / carpenter) instead of named individuals (John Smith / Fred Smith). MS Project doesn’t know this and assumes that each entry in your resource sheet is a single individual.
You know that you’ve got more than one carpenter working on the roof, but MS Project doesn’t. It thinks that the resource you have scheduled to do the roofing has more work assigned than they can physically complete in the allotted timescale. That’s probably why it’s showing as an overallocation.
Try looking at the Resource Graph (View > Resource Graph) and then deciding for yourself whether or not they’re actually overallocated.
As an example if their peak units are 400% but there are five carpenters on the job, then they’re not overallocated. If their peak units are 400% and there are only two carpenters then they are.