Histograme S - Curve for P6

A
Arnold Puy 👤 Member for 19 years 2 months

Hi Sundar,



Unfortunately, you cannot show the value in the histogram. You can do it in Excel Sheet. Just go to Resource assignment copy & paste.



Regards,



Arnold

S
Sundar Singh 👤 Member for 18 years 9 months

Thanks. Can you advice me, how i can show the value in each histogram like P3

K
Khaled Fathi 👤 Member for 18 years 4 months

For the resources S-Curve & Histograme you need to go to Activity window and press the "Resource Usage Profile" in the Activity toolbar and it will open in the bottom where you can select the requiered resources and also you can change the shown details by right click the graph and selecting the "Resource Usage Profile options...".



hope this will help you



Khaled

Forum Sponsor

Top Posters

J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts