a) youre right: I just checked what you said in MSP 2003 and MSP2007, and the result is amazing:
whatever setting you give the task, its duration is 5 day;
unless you give the task a calendar and check the next option saying it will not respect the resources calendar: then the task duration is only 2 days, and MSP does not show the Dick and Harry overallocated!
that means the Effort driven only works when the resources are available at the same time, that makes sense
the problem is: MSP does not show the resource being overallocated
b) MSPs definition for Effort driven as follows: allocate a 1st resource to the task and give it some work, the allocate additional resources to share this amount of work; thats the same as "Fixed work", but between difefrenbt resources
Interesting answer, I never really considered that a task should be resource driven in such a way, but on reflection if you interpret it literally, i.e. unit availability, I suppose it could.
Using MS Project, I have always understood resource driven to mean that the duration of a task is determined by the assignments resource calendars.
As an example:
Tom only works Mon & Tue
Dick only works Wed & Thu
Harry only works Fri
This means if each resource is assigned to work 1 day on a task, the minimum duration would have to be 5d. (Unless you split it of course)
for MSP, resource driven means: Task Duration = Work / Units (one resource per task)
effort driven: Task Duration = Total resources work / Total resources Units (several resources per task)
to drive tasks by the effort, allocate a 1st resource and give her the desired amount of work for the task; then allocate additional resources; the more resources you will have on a same task, the shorter the task will be for the same total amount of work
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Darren,
a) youre right: I just checked what you said in MSP 2003 and MSP2007, and the result is amazing:
whatever setting you give the task, its duration is 5 day;
unless you give the task a calendar and check the next option saying it will not respect the resources calendar: then the task duration is only 2 days, and MSP does not show the Dick and Harry overallocated!
that means the Effort driven only works when the resources are available at the same time, that makes sense
the problem is: MSP does not show the resource being overallocated
b) MSPs definition for Effort driven as follows: allocate a 1st resource to the task and give it some work, the allocate additional resources to share this amount of work; thats the same as "Fixed work", but between difefrenbt resources
Alexandre
Alexandre,
Interesting answer, I never really considered that a task should be resource driven in such a way, but on reflection if you interpret it literally, i.e. unit availability, I suppose it could.
Using MS Project, I have always understood resource driven to mean that the duration of a task is determined by the assignments resource calendars.
As an example:
Tom only works Mon & Tue
Dick only works Wed & Thu
Harry only works Fri
This means if each resource is assigned to work 1 day on a task, the minimum duration would have to be 5d. (Unless you split it of course)
Regards,
Darren
Faisal,
for MSP, resource driven means: Task Duration = Work / Units (one resource per task)
effort driven: Task Duration = Total resources work / Total resources Units (several resources per task)
to drive tasks by the effort, allocate a 1st resource and give her the desired amount of work for the task; then allocate additional resources; the more resources you will have on a same task, the shorter the task will be for the same total amount of work
Alexandre