S Curves in P6 - how?

E
ersin namli 👤 Member for 20 years 10 months

Hi everyone,

This experience, I mean the experience of sharing a file with sending e-mail to everyone one by one has to force us to find an easy way.

is it hard to add a part to planningplanet which we can share our files. I’m sure a facility like that will increase the effectiveness of our conversations and reduces unnecessary explanations.



if there is a file share part sorry about my ignorance

A
Ahmed Abu El Azm 👤 Member for 17 years 5 months

I’d suggest to upload the file on any file sharing website instead of sending it several times.

F
Frankie Jee 👤 Member for 17 years 8 months

hey Arnold...dun no wat r u sending to everyone...



Send me as well :)......i know u must be sending good information to the people

..thankss



[email protected]

A
Arnold Puy 👤 Member for 19 years 1 month



Thumb of rules, for planning quantities is based on your daily requirements for the particular materials. This is where your CM, Site Engineer Works planning or target output to finish the certain quantity for excavation or concreting per day. Based on that, you can then input manually this quantity accordingly.

A
Ahmed Khan 👤 Member for 17 years 6 months

Arnold,



Yeah i need the same thing. The distributions manually. But do U have any thumb rules to assing it according to the quantities.



Regards

Maask

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Maask,



Can you please explain in detail what do you really needs. If you are talking about specific quantities distribution per day, week & month based on your future planning, then you can use future bucket planning which is input manually by the users.



HTH.



Arnold

A
Ahmed Khan 👤 Member for 17 years 6 months

Arnold,



Do U have any idea of distributing the resources for the specific quantities of work. The normally the works are



Excavation

Backfilling

Compaction

Concreting



Regards

Maask

S
Sham Dham 👤 Member for 24 years 9 months

Hi



I am having some difficulty in producing S Curve showing Project Baseline Early Start, Project Baseline Late Finish & Actual.



If anyone can help with step by step guide I would be very grateful.



Many Thanks

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts