The start date signifies the start of the project. The rest of the schedule should be driven by a precedence network. Most, if not all of the activities will have a finish-start relationship, i.e. the next task in the chain will start after the preceding task is complete.
When the first task in your schedule is complete what happens? Does everyone just down tools and hang around or is there something else that happens in the meantime?
If in the unlikely event that nothing else is going to happen, why do you have to start the project on that date?
I can think of a couple of quick workarounds that might help you out, however, from a planning perspective I wouldn’t particularly recommend either of them. It’s just manipulating the scheduling software to show a contrived view of the project.
Option 1
Add soft constraint dates on all the ensuing tasks so they start on the correct dates.
Option 2
Add a lags on all the ensuing tasks so they start on the correct dates.
I did try this but because the tasks after the start date are linked when I amended the start date as you suggested all the follow-up tasks also moved.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Gerry,
I’m a little confused.
The start date signifies the start of the project. The rest of the schedule should be driven by a precedence network. Most, if not all of the activities will have a finish-start relationship, i.e. the next task in the chain will start after the preceding task is complete.
When the first task in your schedule is complete what happens? Does everyone just down tools and hang around or is there something else that happens in the meantime?
If in the unlikely event that nothing else is going to happen, why do you have to start the project on that date?
I can think of a couple of quick workarounds that might help you out, however, from a planning perspective I wouldn’t particularly recommend either of them. It’s just manipulating the scheduling software to show a contrived view of the project.
Option 1
Add soft constraint dates on all the ensuing tasks so they start on the correct dates.
Option 2
Add a lags on all the ensuing tasks so they start on the correct dates.
Regards,
Darren
You dont need to remove all the links but just the key link.
Is there a way of removing the links and puting them back quickly. The only way I know to put them back is one at a time?
I dont think I understand but how about temporarily removing the link?
I did try this but because the tasks after the start date are linked when I amended the start date as you suggested all the follow-up tasks also moved.
Gerry , the following should help
using the top toolbar
project
project information
select your project start date
ok