Oracle Primavera - PM6 Member for 19 years Member for 19 years Submitted by Rama Krishnan on Sat, 2008-11-29 10:36 Permalink RE: Cumulative Early and Late Curves If you have copied activities from another project , constraints of previous project are also copied such as project finish by date or activitys must complete by. These could introduce unwanted negative float Rama Member for 21 years Member for 21 years Submitted by Ian Adan on Thu, 2008-10-30 11:53 Permalink RE: Cumulative Early and Late Curves I guess you have negative float on some of your activities. Log in or register to post comments
Member for 19 years Member for 19 years Submitted by Rama Krishnan on Sat, 2008-11-29 10:36 Permalink RE: Cumulative Early and Late Curves If you have copied activities from another project , constraints of previous project are also copied such as project finish by date or activitys must complete by. These could introduce unwanted negative float Rama
Member for 21 years Member for 21 years Submitted by Ian Adan on Thu, 2008-10-30 11:53 Permalink RE: Cumulative Early and Late Curves I guess you have negative float on some of your activities.
Member for
19 yearsRE: Cumulative Early and Late Curves
If you have copied activities from another project , constraints of previous project are also copied such as project finish by date or activitys must complete by.
These could introduce unwanted negative float
Rama
Member for
21 yearsRE: Cumulative Early and Late Curves
I guess you have negative float on some of your activities.