Bucket planning in P5

Y
Yusuke Kamui 👤 Member for 18 years 1 month

Hi thanks for the reply,

What do you mean, I fixed it? The duration types in P5 are: "Fixed Units", "Fixed Duration & Units", "Fixed Units/Time", "Fixed Duration & Units/Time" only.



Right now the daily budgeted units looks like this:

1-May 2-May 3-May 4-May

Activity xxx 5h 5h 5h 5h



I want it to be changed to:

1-May 2-May 3-May 4-May

Activity xxx 2h 2h 8h 8h





So pls tell me how to do it. Thanks.

A
Arnold Puy 👤 Member for 19 years 2 months

Hi Yusuke,



Try to change the The displayed timescale unit in the spreadsheet is smaller than the minimum timescale unit used for time-distributed resource calculations. You can change this setting in the ’Interval for time-distributed resource calculations’ field (User Preferences, Resource Analysis tab). For example, if this option is set to Week, you can only enter or edit data in weekly, monthly, or quarterly timescale buckets.



If it is still not working try to read "Manually enter or edit future period assignment values" in the help menu.



HTH.



Regards,



Arnold


Forum Sponsor

Top Posters

Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts
Erkan Polater
9 posts