Bucket planning in P5

Y
Yusuke Kamui 👤 Member for 18 years

Hi thanks for the reply,

What do you mean, I fixed it? The duration types in P5 are: "Fixed Units", "Fixed Duration & Units", "Fixed Units/Time", "Fixed Duration & Units/Time" only.



Right now the daily budgeted units looks like this:

1-May 2-May 3-May 4-May

Activity xxx 5h 5h 5h 5h



I want it to be changed to:

1-May 2-May 3-May 4-May

Activity xxx 2h 2h 8h 8h





So pls tell me how to do it. Thanks.

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Yusuke,



Try to change the The displayed timescale unit in the spreadsheet is smaller than the minimum timescale unit used for time-distributed resource calculations. You can change this setting in the ’Interval for time-distributed resource calculations’ field (User Preferences, Resource Analysis tab). For example, if this option is set to Week, you can only enter or edit data in weekly, monthly, or quarterly timescale buckets.



If it is still not working try to read "Manually enter or edit future period assignment values" in the help menu.



HTH.



Regards,



Arnold


Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts