MS Project Issue/Concern.

F
Forum Guest 👤 Member for 17 years 5 months
D
Denise Chapple 👤 Member for 22 years 2 months

Re strange things that MSProject does

Sometimes MSProject crashes when people try to mix and match with different versions. Although MS say the different versions can be converted which then can I don’t think they expected people to move backward and forward in issue. Check the versions but you will have to go back to where you were before it all crashed.

A
Alexandre Faulx-Briole 👤 Member for 23 years 6 months

Hello,

You should manually update the plannings up to the date they had met before the crash; then start again updating by importing the data from Progress Mail.

It appears that MSP understands the tasks have not been worked on between their scheduled start date and the first automatic update.

This behaviour does not come from the Effort setup but from the fact (IMO) that your resources give actual hours per day and not %achieve figures.

Regards

Featured Partner

Top Posters

PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts
Hamzah Ahmed
0 posts
Quinton van Eeden
3 posts
Sunchana Johnston
12 posts
Akram Hammam Mohamed
17 posts
Sagar Raut
14 posts