Using the Contingency reserve

S
Sam Onumah 👤 Member for 18 years 2 months
M
Mike Testro 👤 Member for 20 years 6 months

Hi Sam



It is just an activity bar that is set up for the same duration as the available float.



It is linked between the programmed end date and the contract completion date.



There has been a recent thread on this subject which will give you more details.



Best regards



Mike Testro

S
Sam Onumah 👤 Member for 18 years 2 months

Hi Mike



This reserve has both labor hours and material quantity. It also has some float.

Do you have any document which shows how to build the time contingency risk bar?



Thanks.

M
Mike Testro 👤 Member for 20 years 6 months

Hi Sam



Do you have a time contingency as well as a resource contingency?



In other words is there any spare float in the work package programmes.



Can this float be collected to the end of the work?



If so create a time contingency risk bar to take up the foat and load your surplus hours into the time risk bar.



Only adjust the risk bar for contractor delays and it will be the last activity to get progressed.



I hope this helps.



Best regards



Mike Testro

Forum Sponsor

Top Posters

J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts